Roads works along Hyndford Road, Lanark

Published Tuesday, 23 January 2018

Works began along sections of Hyndford Road, Lanark this week.

Works to carry out the installation of the rising main sewer line along sections of Hyndford Road from Winston Barracks towards Lanark Town Centre, terminating at The Beeches Road began on Monday 22 January 2018.

There will also be some plant movement on the development road between the area of the Pumping Station in the northwest corner of the site to the junction of Hyndford Road.

It is anticipated that these works, which include carriageway excavation, installation of sewer line, manholes, cleaning and resurfacing will be ongoing  for approximately 12 weeks, completing by Monday 16 April 2018.

Tough Construction thanks everyone in advance for their cooperation during this period and apologise for any inconvenience this may cause.

If there are any issues during the works please contact George Brogan, Contracts Manager, Tough Construction on 0141 954 8015.