Gas main replacement works in Hamilton

Published Monday, 11 December 2017

gas worker laying new yellow pipe

A series of gas main replacements will be taking place along Cadzow Street and Muir Street in the New Year.

Unfortunately this means there will be major roadworks being undertaken by Scottish Gas Networks (SGN) on Cadzow Street (from Auchingramont Road to Muir Street) and Muir Street (from Lower Auchingramont Road to Montrose Crescent) from Monday 8 January 2018 to Sunday 25 February 2018.

The project will be carried out on a phased basis:

  • Phase 1: Cadzow Street 8 January to 28 January (Road Closure)
  • Phase 2: Muir Street (westbound) 29 January to 25 February (lane restriction westbound only)

SGN will allow local access to Cadzow Street as far as practicable to ensure that access to businesses and properties within the road closure is maintained, albeit delays should be expected.

The signed diversion route is: Lower Auchingramont Road and Muir Street.

If you require additional information regarding these work please email Scottish Gas Networks or phone 0800 912 1700. Alternatively you can write to them directly:

SGN
Inveralmond House
200 Dunkeld Road
Perth, PH1 3AQ